Validation in SICLIMAT Schedules and Calendars
When you set SICLIMAT Schedules and Calendars target object with Validation profile = Enabled, Monitored or Supervised combined with the Four Eyes check box option, then you are prompted to validate the actions performed to the target object.
Some examples of the performed actions are: Add, Modify, Delete, Save, Copy and Paste.
When the object is modified or updated, all the changes are logged into the Audit Trail log of the validated object and the object version increments are recorded and stored under the right panel, in the History tab.

Users with OIDC or software accounts are not allowed to validate SICLIMAT Schedules and Calendar objects.
The following table displays applicable SICLIMAT Schedules and Calendars target objects with their respective actions:
Validation Profile Target Objects | Action | Validation Output |
SICLIMAT Schedule |
| On saving the changes, Validation required dialog box with corresponding input field is displayed based on the Validation profile. |
SICLIMAT Calendar |
| |
SICLIMAT Schedule exception |
| |
SICLIMAT Scene and data point |
|
Following table displays some more scenarios where multiple objects are validated and their corresponding validation output:
Scenarios for SICLIMAT Schedule | Validation Output | |
SICLIMAT Schedule is not validated | Commanded Output (Scene Object and/or data point) is not validated | Validation required dialog box is not displayed. |
Commanded Output (Scene Object and/or data point) is validated | On modification of SICLIMAT Schedule for Weekly Entries, Exception Entries, or parameters under the Options dialog box, Validation required dialog box with highest Validation profile is displayed. | |
SICLIMAT Schedule is validated | Commanded Output (Scene Object and/or data point) is not validated | On modification of SICLIMAT Schedule for Weekly Entries, Exception Entries, or parameters under the Options dialog box, Validation required dialog box with highest Validation profile is displayed. |
One of the commanded outputs (Scene Object and/or data point) is validated | On modification of SICLIMAT Schedule for Weekly Entries, Exception Entries, or parameters under the Options dialog box, Validation required dialog box with highest Validation profile is displayed. | |
Item | Scenarios for SICLIMAT Calendar | Validation Output |
1 | SICLIMAT Calendar is not validated | Validation required dialog box is not displayed. |
2 | SICLIMAT Calendar is validated | On modification of SICLIMAT Calendar exception entries Validation required dialog box with the highest Validation profile is displayed. |